Managed Lanes South Segment |
Description: In San Diego from 2.4km South of Junction Rte 163 to Route 15/56 Separation. Construct Managed Lanes South Segment (Freeway Component). (TCRP #83)
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Diego |
City | San Diego |
Zip Code | 92123, 92124, 92126, 92128, 92129, 92131, 92145 |
Senate District |
36, 39 |
Assembly District | 75, 77 |
Congressional District | 52 |
Caltrans District |
11 |
County/State Route | San Diego 15 |
Postmile Begin/End | M 10.4 M 19.3 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 29386 | 35,989 |
Lane Miles Added (HOV) | 14.74 | |
Peak Period Time Savings (minutes) | 2145180 | 2,195,131 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Andrew Rice | (619) 688-3284 | andrew.rice@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Andrew Rice | (619) 688-3284 | andrew.rice@dot.ca.gov | |
Right of Way Phase |
Caltrans | Andrew Rice | (619) 688-3284 | andrew.rice@dot.ca.gov | |
Construction Phase |
Caltrans | Andrew Rice | (619) 688-3284 | andrew.rice@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Andrew Rice | (619) 688-3284 | andrew.rice@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
CMIA |
$350,000 | $-74,404 | $275,596 | ||||
Non-bond Funding | |||||||
State/Federal* |
$60,000 | $-51,100 | $8,900 | ||||
Local** |
$71,324 | $-24,739 | $46,585 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $481,324 | $-150,243 | $331,081 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$2,431 | $-2,431 | $0 | $0 | |||
Design(PS&E) |
$59,569 | $-10,364 | $49,205 | $36,730 | |||
Right of Way |
$19,324 | $-13,044 | $6,280 | $2,468 | |||
Construction |
$400,000 | $-124,404 | $275,596 | $267,394 | |||
Total* | $481,324 | $-150,243 | $331,081 | $306,592 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
|
|
12/11/1998 03/27/2003 |
100 | 12/11/1998 03/27/2003 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
07/15/2002 06/30/2008 |
100 | 07/15/2002 02/01/2008 |
0 5 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
08/21/2006 10/01/2007 |
100 | 09/01/2005 08/15/2007 |
12 2 |
|
Begin Construction Phase
End Construction Phase |
|
|
02/25/2008 02/21/2011 |
100 | 05/12/2008 05/31/2011 |
-3 -3 |
|
Begin Closeout Phase
End Closeout Phase |
|
|
01/18/2011 07/20/2012 |
50 | 06/01/2011 02/06/2013 |
-4 -7 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 01/17/2007 | 0 | 0 | ||||
Implementation Date | 01/17/2007 | 0 | 0 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 29386 | 35,989 |
Lane Miles Added (HOV) | 14.74 | |
Peak Period Time Savings (minutes) | 2145180 | 2,195,131 |
Bond Funding Cost | |
---|---|
Adopted: |
$350,000,000 |
Current Approved: |
$280,669,000 |
Actual Expenditures: |
$263,033,000 |
Status as of December 31, 2023.